Updates on Project
Status and Model Development
Fall 2001 to Fall 2003
- Continue model simplification studies
- Start research project for Ohio Coastal
Assistance Grants Management Program to develop tributary habitat maps
- Start of regional stressor-response modeling
project
Fall 2000 to Fall 2001
- Completion of model simplification studies
- Begin GIS mapping of nearshore and tributary
habitat
Fall 1999 to Fall 2000
- Conducted modeling and decision analysis
workshops on the value to fisheries management of research on "Lake
Erie Response to Nutrient Inputs and Zebra Mussels: Workshops (January 24-25 and
February 21-22, 2000).
- Extension of LEEM to include habitat influences
Spring 1997 to Fall 1999
- Participation in the 1999
IAGLR Modelling
Summit
- Analysis of effects of phosphorus loading
constraints on the productive capacity of the fish community of Lake
Erie
- Modification of LEEM to include habitat
constraints on fish reproduction.
- Development of an
interactive help
interface for the LEEM model. This interface provides a detailed
summary of the equations in LEEM Version 1.0.
March 1997
- Official release of LEEM Version 1.0. Version
1.0 was written in Visual Basic 4.0 and is available as a stand-alone
program for both Windows 95/NT and Windows 3.x. This release features
an improved user interface and better integration of the model and
EXCEL spreadsheet templates. The spreadsheet templates have also been
revised for this release.
October 1996:
- Posting of Version 0.3 of Prototype. This
Version has some minor upgrades of output from Version 0.3. Spreasheet
templates, however, are revised in this release. Two input spreadsheets
have been reduced to one and feature easier interaction with simulation
model. Three output spreadsheets have been reduced to one also with
features to improve interaction with model.
- Conclusion of the prototype development and
evaluation with presentations and discussions at the Lake Erie
Modelling Summit, which was organized by the IJC's Lake Erie Task Force
and Environment Canada, Windsor, Ontario. September 1996
- Start of new research program funded by the U.S.
EPA, "Modeling and Multiobjective Risk Decision Tools for Assessment
and Mangement of Great Lakes Ecosystems." This is a joint project
between Johns Hopkins University and Case Western Reserve University.
July 1996
- Release of Version 0.2 of LEEM. The prototype
revision included more detailed resolution of lower trophic levels.
- Completion of Phase II of testing of the LEEM
prototype.
April 1995
- Prototype LEEM released for testing following a
Model Evaluation Workshop hosted by IJC's Lake Erie Task Force in
Windsor, Ontario.
- Internet Home Page set up to distribute copies
of the prototype and reports of the Lake Erie Ecological Modelling
Project.
|
|